大断面巷道交叉点L型切顶卸压护巷机理及应用技术研究

    Research on the mechanism and application of L-shaped roof cutting and pressure relief in intersection of large cross-section roadway

    • 摘要: 针对沿空留巷工作面过异常区新掘探煤巷与风巷交叉点处应力集中造成的大变形情况,采用理论分析、数值模拟及现场实践等方法研究了大断面巷道交叉点L型切顶与未切顶两种条件下围岩支承应力演化规律及塑性区分布形态,揭示了新掘探煤巷切顶对风巷留巷效果的影响机理,并且通过理论计算最小切顶角度与高度;采用FLAC3D数值模拟软件模拟探煤巷不切顶、15°切顶和30°切顶三种情况,结合理论计算综合确定探煤巷15°最优切顶方案,切顶后交叉点应力峰值显著降低,塑性区范围减小,达到对异常区风巷护巷效果,利于工作面安全高效回采;结合现场工程地质条件确定了交叉点区域风巷与探煤巷L型切顶卸压方案及长边100 m+短边6 m的隔孔爆破装药规格等参数;对处于异常区交叉点影响范围内风巷进行补强支护,并进行了补强支护方案预应力场验证,得到了浅部0.15 MPa、深部0.02 MPa的深浅部锚固壳体,验证了支护方案的有效性;现场施工后,对异常区内交叉点影响区风巷控制效果进行60 d监测,顶板及两帮变形量显著降低,实现了交叉点区域巷道围岩切顶卸压护巷。

       

      Abstract: In response to the problem of large deformation caused by the stress concentration at the intersection of the newly excavated coal exploration roadway and the air roadway in the goaf-retained working face when passing through the abnormal area. Theoretical analysis, numerical simulation and field practice are used to study the evolution law of bearing stress and the distribution pattern of plastic zone in the surrounding rock of the intersection of large cross-section roadway under L-shaped roof cutting and uncut schemes. The mechanism that the influence of roof cutting in newly excavated coal roadway on the retention effect of air roadway is revealed. The minimum cutting angle and height are calculated theoretically. The effect of three situations of not roof cutting, roof cutting at 15° and roof roof cutting at 30° in the coal roadway is simulated by using FLAC3D. It is determined that under the scheme of roof cutting of the exploration coal road at 15° is the best scheme. After the roof cutting, the stress peak at the intersection is significantly reduced and the plastic zone range is reduced. The effect of protecting the air roadway in the abnormal area is achieved and it is conducive to the safe and efficient mining of the working face. Combined with the engineering geological conditions on site, the L-shaped roof cutting that long side 100 m + short side 6 m and pressure relief scheme and blasting parameters such as blasting charge specifications are determined. The reinforcement support scheme for the air duct in the influence area is designed and the prestress effect is verified by numerical simulation that deep and shallow anchored shells with a shallow pressure of 0.15 MPa and a deep pressure of 0.02 MPa are obtained. After the on-site construction, the control effect of the road is monitored in 60 d. The field feedback shows that the deformation of the roof and two sides is reduced and the surrounding rock of the roadway in the intersection area is cut well to protect the roadway.

       

    /

    返回文章
    返回