    Flood calculation and flood regulation simulation of a multi-branch ditch tailings pond

    • 摘要: 多支沟形成的尾矿库采用不同的计算方式进行洪水计算来确定最大洪水总量。在一个或两个排洪设施并行泄流能力条件下,对该尾矿库进行了调洪演算,研究结果可为多支沟类型的尾矿库汛期安全度汛提供借鉴和相应的依据。

       

      Abstract: For tailings ponds formed by multiple branch ditches, different calculation methods are adopted for flood calculation to determine the maximum total flood volume. Under the condition of the parallel discharge capacity of one or two flood discharge facilities, the flood regulation simulation of this tailings pond is carried out. The research results can provide reference and corresponding basis for the safe flood control of multi-branch ditch type tailings ponds during the flood season.

       

    /