大断面斜井机械化快速施工组织设计研究

    Study on mechanical high-speed construction organization design of large section shaft

    • 摘要: 施工组织设计是指导项目工程建设的重要技术经济性文件。禾草沟煤矿副斜井基岩段长度1533.7m,掘进断面面积21.6m2,属于大断面超长斜井。禾草沟煤矿根据具体地质情况,优化施工组织设计,采用"四八交叉制"循环作业方式,运用大功率EBZ318H型综掘机掘进,实现了斜井快速施工,取得了最高月进227m的好成绩,工程质量优良,未发生安全事故,实现了安全高效、优质快速施工,经济效益和社会效益明显,为同类大断面超长斜井施工方面积累了丰富的经验。

       

      Abstract: Construction organization design is an important technical and economic document.The length of bedrock section of auxiliary inclined shaft in Hecaogou mine is 1533.7m.The area of driving section is 21.6m2,belongs to large section super-long shaft.According to concrete geological conditions,Hecaogou mine optimized the construction organization design,used "four-eight cross system" cyclic operation,used high power EBZ318H fully-mechanized coal winning machine to drive,realized rapid construction of inclined shaft,achieved good results that the highest speed was 227m per month.And it ensured good engineering quality,safety and high efficiency,high quality and quick speed construction.The economic and social benefits were significantly.For similar large section super-long shaft construction,this construction organization design accumulated rich experience.

       

    /

    返回文章
    返回