UDEC在急倾斜特厚煤层开采沉陷数值模拟中的应用
UDEC in the steep thick seam mining subsidence in the application of numerical simulation
-
摘要: 随着城市的不断发展扩大,位于城市周边的煤矿开采沉陷盆地对城市的安全和发展构成了严重的威胁和障碍,为治理煤矿采空塌陷区,恢复土地的使用功能,需要研究地下矿床开采引起围岩和地表覆盖层破坏规律。通过UDEC数值计算软件,利用离散元方法,研究了急倾斜特厚煤层开采围岩破坏规律,地表变形规律,分析其变形破坏特征及主要运移规律。得出急倾斜特厚煤层开采破坏主要向煤层上方发展,老顶的存在有效限制了破坏向顶板的发展,底板侧的破坏较小,地表呈深槽型地表塌陷坑,提出在开采过程中分段或水平采用自上而下的充填采矿方法可以及时有效的控制围岩破断的影响范围,在老顶上方就可构筑永久绿化带和建筑物,恢复土地的使用功能。Abstract: With the continuous development of the expansion of the city, located in the peri-urban settlement of the coal mining basin of the city's security and development pose a serious threat and obstacle to treatment for the coal mined-out area collapse, to resume the land use functions, need to look at the ground floor deposit Caused by mining and surface rock cover damage to the law. UDEC through numerical simulation software, using discrete element method to study the steep thick seam mining damage to surrounding law, the law of surface deformation, deformation and failure analysis of its main characteristics and migration laws. Steep come thick seam mining damage to the main coal seam at the top of the development, the existence of an effective roof limited the damage to the roof of the development side of the floor of the destruction of small, dark surface groove surface subsidence pits, put forward in the process of exploitation Or the use of sub-standard top-down mining method can be filled in a timely and effective control of the surrounding rock breaking the affected area, on top of the old side can build permanent buildings and green belts, the use of the land to restore functionality.
下载: