7m大采高综采工作面末采安全高效贯通实践

    Discussion about the safe and efficient mining of 7m large mining height through the end of fully-mechanized face

    • 摘要: 基于大柳塔煤矿7m大采高综采工作面末采贯通现场实践,采用对比分析、现场观测与工程实践相结合的方法,分析了大采高综采工作面在末采贯通中存在的问题,并从设备选型、技术措施和管理等方面提出了解决方法。

       

      Abstract: In order to summarize the experience of 7m large miningheight through the end of fully-mechanized face,this paper is based on the field practice of 52303 large mining height through the end of fully-mechanized face,combining with the use of comparative analysis,field observations and engineering practice,analyzing the issue of through the end of the surface.Finally,in order to provide technical support and accumulate experience for the safe and efficient mine production,we put forward the technical,design,equipment selection,hanging process,knowledge of management and other aspects of the targeted technical measures.

       

    /