张福民, 张东峰, 张小强, 侯建. 深井沿空巷道合理位置确定及围岩控制技术[J]. 中国矿业, 2020, 29(11): 136-141,146. DOI: 10.12075/j.issn.1004-4051.2020.11.009
    引用本文: 张福民, 张东峰, 张小强, 侯建. 深井沿空巷道合理位置确定及围岩控制技术[J]. 中国矿业, 2020, 29(11): 136-141,146. DOI: 10.12075/j.issn.1004-4051.2020.11.009
    ZHANG Fumin, ZHANG Dongfeng, ZHANG Xiaoqiang, HOU Jian. Reasonable location determination and surrounding rock controlof deep well gob roadway[J]. CHINA MINING MAGAZINE, 2020, 29(11): 136-141,146. DOI: 10.12075/j.issn.1004-4051.2020.11.009
    Citation: ZHANG Fumin, ZHANG Dongfeng, ZHANG Xiaoqiang, HOU Jian. Reasonable location determination and surrounding rock controlof deep well gob roadway[J]. CHINA MINING MAGAZINE, 2020, 29(11): 136-141,146. DOI: 10.12075/j.issn.1004-4051.2020.11.009

    深井沿空巷道合理位置确定及围岩控制技术

    Reasonable location determination and surrounding rock controlof deep well gob roadway

    • 摘要: 针对深井高地应力矿井煤柱应力大、巷道围岩变形严重及煤柱宽度大造成资源浪费等特点,以麦地掌煤业21214工作面为研究背景,通过地应力测试、钻孔应力测试了解工作面侧向应力峰值位置及大小。根据现场实测及分析得到侧向应力峰值约为43 MPa,且位于距巷帮约17 m处。运用理论计算、数值模拟,研究沿空掘巷围岩在掘采期间的变形破坏特征、合理窄煤柱尺寸的确定及沿空巷道的围岩控制。结果表明:煤柱宽度为6.5 m时巷道围岩稳定性较好,掘进初期,围岩变形量及变形速率较大,后逐渐减小,掘进影响期为15 d,回采期间由于小煤柱侧的支护强度大于工作面侧,小煤柱侧的变形量小于工作面侧的变形量,最大变形量分别为110 mm和248 mm,均在可控的范围内。

       

      Abstract: In view of the characteristics of large stress on coal pillars, serious deformation of roadway surrounding rock and waste of resources caused by large width of coal pillars in deep shaft and high-in-situ stress mine, 21214 working face of Maidizhang coal industry is taken as the research background to understand the position and size of lateral stress peak on working face through in-situ stress test and borehole stress test.Through field measurement and analysis, the lateral stress peak value is about 43 MPa, which is located about 17 m away from the roadway side.Based on theoretical calculation and numerical simulation, the deformation and failure characteristics of surrounding rock during excavation and mining, determination of reasonable size of narrow coal pillar and surrounding rock control of roadway along gob are studied.The results show that the coal pillar width is 6.5 m of roadway surrounding rock stability is good, early excavation, the surrounding rock deformation and deformation rate is bigger, after gradually decreases, and tunneling effect period for 15 days, because the small coal pillar side during the period of stoping support strength is greater than the face side, the side of the small coal pillar deformation is less than the deformation of the face side, the maximum deformation of 110 mm and 248 mm respectively, both in the controllable range.

       

    /

    返回文章
    返回